Procurement procedures in Sweden

The procedure sets the rules of a tender: who may bid, whether the buyer may negotiate and how much time you have. Which procedures the buyer may use depends mainly on whether the contract is above or below the threshold.

Updated

Above the threshold

ProcedureHow it works
Open (öppet förfarande)Anyone may bid, no negotiation. At least 35 days, 30 with electronic submission.
Restricted (selektivt)Companies apply first; qualified ones are invited to bid, at least five if the number is limited.
Competitive procedure with negotiationLike restricted, but the buyer may negotiate.
Competitive dialogueThe buyer develops the solution with selected companies, then asks for final bids.
Negotiated without prior publicationExceptions, such as only one possible supplier or extreme urgency.

Below the threshold

  • Simplified procedure (förenklat förfarande): anyone may bid; negotiation is allowed if the notice says so. The most common procedure in Swedish municipalities.
  • Selection procedure (urvalsförfarande): companies apply first and some are invited to bid.
  • [Direct award](/guider/direktupphandling/): below SEK 700,000, no notice needed.

Below the threshold the deadline must be reasonable, in practice often two to three weeks.

Dynamic purchasing systems

A dynamic purchasing system is fully electronic and open for its whole term. Unlike a framework agreement, new suppliers can join at any time by meeting the qualification requirements. Each contract is then competed among the suppliers in the system.

Frequently asked questions

What is förenklat förfarande?
The simplified procedure used below the EU threshold. Anyone may bid, and the buyer may negotiate if the notice says so.

This guide is a general description, not legal advice. Laws and amounts can change; the Swedish National Agency for Public Procurement (Upphandlingsmyndigheten) has the latest figures.